UP- RERA cancelled the registration of three housing projects in Ghaziabad

Uttar Pradesh Real Estate Regulatory Authority cancelled the registration of Antriksh Sanskriti Phase 2,3 and Raksha Vigyaan Sanskriti phase 2 under RERA section 8.

On Wednesday UP-RERA announced that the registration of three incomplete group housing projects has been cancelled in Ghaziabad over work delay. Their bank accounts are frozen, to prevent transactions.

UP-RERA informed “Multiple complaints were lodged by the allottees of two projects of M/s Antriksh Realtek Pvt. Ltd and a project of Raksha Vigyan Karmacharis Sahkaari Samiti Ltd. with the Authority under Section 31 of the RERA Act, alleging the violation of the agreement/contract with the promoter and delay in construction.”

According to the promoter, the construction work of the projects began in 2015 and completion dates were July 2022 for phase 2,3 and June 2023 for Vigyaan Sanskriti phase 2.

UP RERA shared “As per on-site verification report of projects received by UP RERA, presently, the construction and development work has been achieved up to 40 per cent in Antriksha Sanskriti Phase-2 and up to 30 per cent in Antriksha Sanskriti Phase-3. Surprisingly, the construction and development work could not commence in Raksha Vigyaan Sanskriti Phase-2.”

“The inspection report also states that all kinds of construction work on the project site are closed for many years, thus the chances of completion of the projects are absolutely uncertain,” it added.

The statement added “This information has been conveyed to RERA offices of other states and Union Territories. It has been decided by the Authority to freeze bank accounts of projects to prevent any kind of transactions related to the project,”

According to the statement, the Project Advisory and Monitoring Committee includes the vice-chairman of the Ghaziabad Development Authority together with a technical advisor, conciliation consultant, auditor of UP RERA, financial institutions and association of allottees responsible for the project.

Expert assistance will be provided to this committee from the Project Management Division of UP RERA to ensure the completion of the project, it added.

Follow and Connect with us: Twitter, Facebook, Linkedin, Instagram

Anamika Gairola

Anamika is a research-oriented writer with experience in writing blogs on home decor and real estate industry. Simply put, she knows the trend and expectations of today’s industry. She is an avid reader, wishes to travel the world, and loves to cook her favorite recipes when not writing.

Share
Published by
Anamika Gairola

Recent Posts

Maha RERA directs Godrej Properties to refund the booking amount for a project initiated before RERA regulations.

The regulator determined that the project was ongoing when the real estate law came into…

1 day ago

The Importance of Due Diligence Before Purchasing Property

Due Diligence Before Purchasing Property, Due diligence is an essential step in any real estate…

5 days ago

Embassy Real Estate Investment Trust (REIT) has appointed Ritwik Bhattacharjee as the interim CEO.

This follows a SEBI order on November 4 directing Embassy REIT to suspend Aravind Maiya…

6 days ago

Macrotech acquires Bain Capital’s stake in three digital infrastructure entities for ₹307 crore.

Previously, Macrotech also acquired real estate firm Ivanhoe Cambridge's stake in the three entities, aligning…

1 week ago

Benefits of LEED-Certified Buildings for Investors and Tenants

LEED (Leadership in Energy and Environmental Design) certification has become a prestigious standard in the…

1 week ago

QIP issuances by real estate developers reached ₹12,801 crore from January to September 2024, marking the second-highest amount after the renewable energy sector

From January to September 2024, QIP issuances across all sectors totaled ₹75,923 crore, with real…

2 weeks ago

This website uses cookies.