There were many complaints filed by the investors of Wish Town in Noida against the company and therefore a combined FIR was lodged by the police. After the FIR, the company had promised that the construction would start phase by phase.
Currently, construction materials can be seen at the construction sites and the work of cement layering was also going on. Even the work of electrical details was in progress. But the fact remains that the number of labourers was still not sufficient to match the level of construction that is still left.
The management of Jaypee had assured the homebuyers that it is completely dedicated towards completing the Wish Town in Noida, with the support of the working capital it received from banks.
As per the layout and completion roadmap of the company, the number of flats which will be delivered by 2018 is 6000, by 2018-19 is 8000 and the remaining will be delivered by 2020.
Minimalist interior design has become a global trend, celebrated for its simplicity, elegance, and functionality.…
The real estate sector in India, traditionally known for its slow-paced processes and manual operations,…
The real estate sector, traditionally a playground for high-net-worth individuals, is undergoing a transformation with…
Real estate experts highlighted that the strong response reflects the growing residential demand in the…
According to the company, Bagri brings extensive expertise in corporate finance, controllership, treasury, strategic planning,…
Artificial Intelligence (AI) and Machine Learning (ML) are revolutionizing personal finance by transforming how individuals…
This website uses cookies.