Homebuyers alleged being cheated by the developer and protested

Construction of the remaining 13 towers of Supertech Basera has been at rest for 3 years, which delayed the possession of flats. Homebuyers protested against the developer at the project site and filed a complaint at CM window.

A group of homebuyers gathered and protested against the Supertech Basera at the project site on Sunday for the delay in delivery of their flats.

The housing project was launched in 2015, promising the possession of flats by 2020. But the developer has offered only two towers partly, while the remaining 13 towers are constructed only 50%.

Homebuyers said that the project has 15 towers having 1,976 flats. “The project is delayed by three years and most of us have fully paid the developer and are now feeling cheated. We all are losing hope of getting our flats as the developer does not want to complete this project,” said Ashis Soni, one of the homebuyers.

Another homebuyer Ravinder Singh said that he had booked a flat in 2015 supposed to get possession by 2020, but now he doesn’t know when he will be able to move into his flat. They filed the complaint at the CM window and contacted authorities seeking their intervention in expediting the project but to no avail. Now they don’t have any other option instead of protesting.

Mohit Arora, MD of Supertech said that possessions at Basera are going on a regular basis and flats are being handed over every week. The buyers are regularly updated on the construction progress. The construction work is now back on track after hurdles of the NGT construction ban and all the flats will be delivered in the next 12 months.

Follow and Connect with us: Twitter, Facebook, Linkedin, Instagram

Team iPropUnited

Share
Published by
Team iPropUnited

Recent Posts

The Power of Networking for Small and Medium Enterprises (SMEs)

In the dynamic world of business, networking has emerged as a cornerstone for the growth…

3 weeks ago

Adani Group inks MoU with the Odisha government for a ₹2.3 lakh crore investment over the next five years.

The MoU was signed at the ‘Utkarsh Odisha-Make in Odisha Conclave,’ inaugurated earlier in the…

4 weeks ago

Land deals surge by 48% in 2024, with Delhi-NCR taking the lead

Over 40 land deals were recorded in the Delhi-NCR micro-market, with Gurugram contributing to 60%…

1 month ago

Personal Finance Tips for Young Professionals

As a young professional, building a strong financial foundation early in your career can set…

2 months ago

The Importance of ESG (Environmental, Social, and Governance) in Modern Business

In recent years, ESG (Environmental, Social, and Governance) has become a critical framework for evaluating…

2 months ago

Why Premium Housing is Gaining Popularity Among Millennials

In recent years, the demand for premium housing has seen a significant rise among millennials,…

2 months ago

This website uses cookies.